E3DDS SG Meeting 20180904
E3DDS steering group meeting
Time: 2018-09-04 11h00 CEST
Place: https://cscfi.zoom.us/j/9917669499
Invitations:
- Craig Heinselman, EISCAT
- Yasunobu Ogawa, EISCAT
- Tomasz Malkiewicz, NeIC, Project owner
- John White, NeIC, Project manager
Agenda
Presence, approval of agenda (5')
Present:
- Craig Heinselman, EISCAT
- Tomasz Malkiewicz, NeIC, Project owner
- John White, NeIC, Project manager
- Yasunobu Ogawa, EISCAT (late-joining)
Collaboration Agreement (CA)
- Signature from Sigma2 missing
We have all signatures now. Sigma2 and EISCAT.
Unique agreement in NeIC history.
Quote from CA:
- CSC, SNIC, UNINETT Sigma2 The three NPs, CSC, SNIC, UNINETT Sigma2, will provide 0.75 FTEs (0.25 FTE each of the three) and e-infrastructure resources (including computing, storage and networks) as in-kind contributions.
Project status
- Project runs nicely... enthusiastic: https://wiki.neic.no/int/E3DDS#Meetings
Kick-off
- Meeting in Uppsala in conjunction with the EISCAT User meeting: https://wiki.neic.no/wiki/E3DDS_Kick-off_meeting
17 attendees, project work set-up and even some hardware discussions.
Project Plan
- The project plan:
- PDF form at: https://wiki.neic.no/wiki/EISCAT_3D_Data_Solutions#Documents
- The google docs version is at: https://docs.google.com/document/d/1rgO0qtHJR6zjigdQ2KytFD3ySLH11XvasvSpJNCBVGg/
Kiruna meeting
- Friday June 1st 08:30-17:00 CET! All-day meeting, well worth the effort.
- https://wiki.neic.no/wiki/E3DDS_Deliverable1_Requirements_meeting
- Deliverable 1 work clarified,
- Deliverable 2 also understood.
- Some interesting questions about ring-buffer sizes required.
Deliverable 1
- Due end of October 2018
- Mostly written, see: https://www.overleaf.com/17176439ggnkpqdgjxyt
- Overleaf (LaTeX)
- Some questions about the file-writer.
Deliverable 2
- Work started.
- FIR filter code available.
- Testing on national provider hardware (AVX256/512)
- Aid from national provider staff to understand perforemance.
- Started to consider the input simulated data (FSRU output)
- Harri onto this with the FSRU project
Milestone 1
- CodeRefinery
- Still to be determined. CodeRefinery project in phase 2 now...
Milestone 2
- Dialog with software architect
- Overall software architect TDB?
- We meet with Harri, Assar weekly
Network meeting
- Remote participation from me (logistics that day!)
Stakeholder meeting
- Sept 17th, Helsingor DK
- Agenda at: https://wiki.neic.no/wiki/E3DDS_Stakeholder_20180917
- As of June 26th 11 people registered (info from NN organizers)
Documents from E3DS
MD-2: Report on requirements for user’s access to the data archive.
We have contributed to the FIM4R document at:
https://docs.google.com/document/d/1aTPJRjXES9sKVn5tp6O_fBN295o7oBET2tXrV1FzsJQ/
FIM4R document published at: https://doi.org/10.5281/zenodo.1296031
MA-4
Documents in place. We have also used this document collection for the Dellingr high-level track as an procurement examples.
MC-3
Nearly done. I have waited for LOFAR but got no good response. Will finish up.
Next Meeting
Proposal:
Minutes
Presence, approval of agenda (5')
- All present.
- Craig Heinselman, EISCAT
- Tomasz Malkiewicz, NeIC, Project owner
- John White, NeIC, Project manager
- Yasunobu Ogawa, EISCAT (late-joining)
- Agenda approved.
Collaboration Agreement (CA)
- We have all signatures now. Sigma2 and EISCAT.
- Unique agreement in NeIC history.
- CSC, SNIC, UNINETT Sigma2 The three NPs, CSC, SNIC, UNINETT Sigma2, will provide 0.75 FTEs (0.25 FTE each of the three) and e-infrastructure resources (including computing, storage and networks) as in-kind contributions.
Project status
- No questions received.
Kick-off
- No questions recei* January 2019 online 10-12 noon CET
- May 2019 F2F at Uppsala, 14 -16 CEST
ved.
Project Plan
- No questions received.
Kiruna meeting
- No questions received.
Deliverable 1
- No questions received.
Deliverable 2
- No questions received.
Milestone 1
Comment: Craig: Agree. Three day workshop too long for us.
Milestone 2
Question: Tomasz: Is there now a person in charge of software? A: Craig: We have completed the interviews. Have a verbal agreement to join. Need to wait for the Head of Admin to return. We don't know officially the notice period at the other end.
Q: Tomasz: What type of work is foreseen? A: Craig: Will be part of EISCAT_3D team. Mostly the FPGA-level work and interfaces.
Q: Tomasz: Will there be a percentage of time for E3DDS? A: Craig: To be determined. Will work under the Project Manager Johan Svensson.
C: Craig: Will work first on the output to ring-buffer. (Good!)
Network meeting
- No questions received.
Stakeholder meeting
Comment: Craig: I won't be able to make it but Carl-Fredrik, Ingemar will be there.
Documents from E3DS
MD-2: Report on requirements for user’s access to the data archive.
Comment: Document accepted by the SG.
MA-4
Comment: Document accepted by the SG.
MC-3
Comment: Document ongoing.
Next Meeting
Comment: Yasunobu: EISCAT User meeting is a good time/place... Uppsala May 2019. Comment: Tomasz: January... Propose Wednesday January 16th time: 10h00-12h00 CET OK?
(Accepted)
- Proposal:
- January 2019 online 10-12 noon CET
- May 2019 F2F at Uppsala, 14 -16 CEST