Goals of the meeting
- Plan who is doing/delivers what and when during the first project year (or until the next project's annual meeting).
- Ensure everyone can start working right away after the meeting (knows peers, has collaboration tools in place, ...).
- Socializing with your colleagues.
Intended Audience
- ESM team/staff
- ESM steering group
- NeIC director, administrative coordinator
Dates & Location
Dates: April 04-05 2017, noon to afternoon
Location: DMI, Copenhagen
Travel Info
Please see the PDF for information on how to get to DMI and for some hotel recommendations.
Schedule
April 4
- 12:00 arrival
- 12:00 - 13:00 lunch (jointly with NordicESM project)
- 13:00 - 13:45 PRACE (jointly with NordicESM)
- 13:45 - 14:30 Group discussions on PRACE?
- 14:30 - 15:00 coffee break
- 15:00 - 16:45 Welcome & Introduction
- Logistics 10' (Thomas)
- Welcome & Goals of the kickoff & NeIC primer 20' (Gudmund)
- Partner presentations (people, vision for ESM) 45'
- Project overview & status 30' (Thomas)
- 19:00 - 21:00 dinner at Thai Pan
April 5
- 09:00 - 09:10 Welcome address by Ulrik Smith Korsholm (DMI, Director of Research and Development)
- 09:10 - 10:30 Activity presentation & planning (45' per activity)
- general intro, overall goals, goals for Y1+, dependencies among activities by activity leaders
- status of work
- deliverables in Y1+ (every deliverable due until March 2018 or M15)
- planning for next 12 months (April 2017 - March 2018): What, Who, When (everyone)
- Activity A - ESGF data node administration and use
- Activity B - ESM competence building
- 10:30 - 11:00 coffee break
- 11:00 - 12:30 Activity presentation & planning (45' per activity)
- general intro, overall goals, goals for Y1+, dependencies among activities by activity leaders
- status of work
- deliverables in Y1+ (every deliverable due until March 2018 or M15)
- planning for next 12 months (April 2017 - March 2018): What, Who, When (everyone)
- Activity C - ESM data quality control
- Activity M - Project Management
- 12:30 - 13:30 lunch
- 13:30 - 15:00 Wrap-up
- further planning for next 12 months (April 2017 - March 2018): What, Who, When (everyone)
- meeting feedback
- misc
- 15:00 departure